Ntabamoya Private Resereve

Drakensberg dwarf chameleon

Drakensberg Dwarf chameleon (Brachypodion dracomontanum) spotted by Karen Zunckels of Karen Zunckels Environmental Consulting.

Photo ©2003 David Totman

Updates

These are the latest updates on progress at Ntabamoya Private Reserve.

16 houses completed

05 August 2010

Shares in farm sold to co-owners.

16 houses completed

05 April 2010

Sixteen houses have been completed.

Shares in the reserve offered to owners

05 April 2009

Owners within the development can now take a proactive share in the reserve by purchasing a 1/25 share for R140,000 (+ VAT if applicable).

"Real Rights" mortgages made available

05 March 2007

OOBA (formerly MortageSA) have made available "Real Rights" mortgages allowing purchasers to purchase a house off-plan and have it fininshed to their particular specifications.

Kudu's introduce themselves

28 October 2009

Two Kudu jumped into the reserve (over a 2,4m fence)

Sites sold

28 February 2007

Three more sites have been sold to co-developers and ths brings the total sales to 18 out of 25.

Exotic species eradicated

09 January 2007

Our priogramme of eradication of exotic species is in full swing and the Lantana plant crop has been significantly reduced by on-site manager Willie Goosen. We intend to keep up this progress and hope to eradicate the species in the next year.

Construction intensifies

20 November 2006

Four houses are now completed and construction of a further four houses is starting.

Zebras introduced

20 September 2006

8 Zebra were introduced as part of the stocking rogramme.

Sites sold

20 June 2006

Four sites have been sold to co-developers and ths brings the total sales to 13 ou of 25.

Construction intensifies

20 November 2006

Four houses are now completed and construction of a further four is starting.

Sectional register opened

20 October 2005

The sectional register has now been opened allowing "Real Rights of Extension" to be issued to all purchasers. This means that purchasers may commence building works immediately, building schdule permitting. Please contact the developer to ascertain the building schedule.

Sectional register

02 September 2005

The layout plan has been certified by the DFA committee and the deeds office process will commence in the next week.

Single storey house plan approval

04 August 2005

The single storey plans have been approved. See Building approval for details.

Single storey house plan application

17 May 2005

The single storey plans are being reviewed by the municipality. The expected completion of the process is mid-July 2005

Sectional Register

10 May 2005

Surveyor General subsectioning process was completed 10 May 2005. The registration of the Sectional Title and creation of Title Deeds commences. Expected completion of this process is 23rd July 2005

Surveyor General

26 April 2005

Sectional register process is under way with the Surveyor General subsection in progress. Expected completion of registration process is 17 May 2005

Single storey house plan application

25 January 2005

A 185m2 single storey plan has been verbally approved by the municipality. Expected completion of the process is 15 May 2005

Single storey

25 January 2005

A 185m2 single storey plan has been submitted for approval by the municipality. The single storey plan is smaller (185m2) and lends itself to the less sloped sites, being 14,7m x 11.4m (see the double storey floor plans)

Showhouse

10 January 2005

The double storey showhouse construction is under way and completion is expected early March 2005. The showhouse is being built to an upmarket specification using floor plan option 2 (see the double storey floor plans)

house plans

13 December 2004

A single storey house design has been submitted for approval. The design is in the same style as the double storey. It has a large living room, separate dining area, 1 en-suite bedroom, 2 further bedrooms and a communal bathroom. The single storey is only 185m2 in floor area providing a less costly design. View the single storey house design.

Building

18 November 2004

Building works on first two houses commences.

Infrastructure, electrical

10 November 2004

Electrical infrastructure installed and tested. 400V -> 3300V -> 400V intermediate system uses underground cables to power 5 houses from each of 5 transformers. In addition there are 2 transformers that supply power to the borehole and reservoir, and the main dam to supply brown water for irrigation in the development area.

Infrastructure, water

05 November 2004

Borehole pump installed and tested.

Certificate of Compliance

27 October 2004

Certificate of compliance for infrastructure obtained from provincial administration.

Infrastructure

20 October 2004

Trenchwork for infrastructure, water and electricity completed.

Infrastructure, electrical

15 October 2004

Transformers and IV cable on-site.

Borehole installed

20 October 2004

Borehole installed and tested to 5000 litres per hour. Rated at 1500 litres per hour continuously.

Updated agreement of sale

20 October 2004

Updated Agreement of Sale, 11 November 2004, version 2.7.

Developers' newsletter

20 October 2004

Developers newsletter providing information and status regarding the development.

Levy estimates

18 October 2004

View the current levy estimates. These have been reduced and include costs for all aspects of maintaining the development area.

Infrastructure page

16 September 2004

View the current state of the infrastructure installation. This includes status on water, electricity, roads, drainage, and sewage.

Infrastructure - Electrical

31 July 2004

Seven of the eight transformers have been custom manufactured and are on-site. Installation points have been constructed in preparation for the electrical installation scheduled for October week 1. All electrical supply points are being pre-fabricated and tested in Bloemfontein in preparation for a quick and faultless installation.

Dam 1 enlargement complete

23 July 2004

Dam 1 has successfully been enlarged as planned. This enlargement project has been brought forward from phase 2 to phase 1 in order to expedite the riverine redevelopment and to provide garden irrigation for the development area.

Updated building specifications

12 July 2004

View the Building specifications for each house.

Agreement of sale, version 1

07 July 2004

View the Agreement of Sale: Version 1, 7 July 2004. (Owners only)

Building contract, version 1

07 July 2004

View the Building contract: Version 1, 7 July 2004. (Owners only)

Proposed management rules

07 July 2004

View the Body Corporate: Proposed Management Rules, Draft 2, 07 July 2004. (Owners only)
These form the basis of the management rules and will be enhanced as the project progresses.

Proposed conduct rules

07 July 2004

View the Body Corporate: Proposed Conduct Rules, Draft 2, 07 July 2004. (Owners only)
These form the basis of the conduct rules and will be enhanced as the project progresses.

Water reservoir - Tank one

28 June 2004

Water reservoir one has been installed. It is a solid concrete tank holding 88,000l of potable water. A second tank will be installed as soon as phase 2 commences.

Project plans

20 June 2004

There are now two project plans that show the status of tasks related to The Reserve and The Development. Go to the Owners area for details of Project plans, legal documents. (Owners only)

Owners area

12 June 2004

There is a Owners Area containing information and documents for those who have reserved units in Ntabamoya Private Reserve. (Owners only)

Site map with views from each site

11 June 2004

See the Site map with views from each site showing North, East, South and West outlooks as well as sold houses and sites.

Questions and Answers

15 May 2004

Questions and Answers have been updated.

Pricing

28 April 2004

The pricing of units was finalised and published last week. See the price list for details of house and site prices.

Created by Aziso